Delhi Metro

DMRC

DELHI METRO RAIL CORPORATION LTD




PRESENT NETWORK

Operational Network: 317 km
Number of Stations: 231

Network Map

 

  • Line 1 (Dilshad Garden – Rithala) – Red Line

Line – 1 (Dilshad Garden – Rithala) was made operational for commercial services in four stages:

(1) Shahdara – Tis Hazari : with effect from 25th December, 2002 (Phase – I).

(2) Tis Hazari – Inderlok : with effect from 4th October, 2003 (Phase – I).

(3) Inderlok – Rithala : with effect from 1st April, 2004 (Phase – I).

(4) Dilshad Garden – Shahdara : with effect from 3rd June 2008 (Phase – II).

  • Line 2 ( HUDA City Centre – Jahangirpuri) – Yellow Line

Line – 2 (HUDA City Centre – Jahangirpuri) was made operational for commercial services in five stages:

(1) Vishwavidyalaya – Kashmere Gate : with effect from 20th December, 2004 (Phase – I).

(2) Kashmere Gate – Central Secretariat : with effect from 3rd July, 2005 (Phase – I).

(3) Vishwavidyalaya – Jahangirpuri : with effect from 3rd February 2009 (Phase – II).

(4) HUDA City Centre – Qutab Minar : with effect from 21st June 2010 (Phase – II).

(5) Central Secretariat – Qutab Minar : with effect from 3rd September 2010 (Phase – II).

(6) Jahangirpuri – Samaypur Badli ( extension of Line-2 ) with effect from 10th November, 2015 Phase III

  • Line 3 (Dwarka Sector 21 – Noida City Centre) – Blue Line

Line – 3 (Dwarka Sector 21 – Noida City Centre) was made operational for commercial services in six stages:

(1) Barakhamba – Dwarka : with effect from 31st December 2005 (Phase – I)

(2) Dwarka – Dwarka Sector 9 : with effect from 1st April 2006 (Phase – I).

(3) Barakhamba – Indraprastha : with effect from 11th November 2006 (Phase – I).

(4) Indraprastha – Yamuna Bank : with effect from 10th May 2009 (Phase – II).

(5) Yamuna Bank – Noida City Centre : with effect from 13th November 2009 (Phase – II).

(6) Dwarka sector 9 – Dwarka Sector 21 : with effect from 30th October 2010 (Phase – II).

  • Line 4 (Yamuna Bank – Vaishali) – Blue Line

Anand Vihar ISBT – Vaishali : with effect from 27th January 2010 (Phase – II).

  • Line 5 (Inderlok – Mundka) – Green Line

Kirti Nagar- Ashok Park main : with effect from 27th August 2011.

City Park (Bahadurgarh) to Mundka: with effect from 24th June 2018.

Line 6 (Kashmere Gate- Raja Nahar Singh ) – Violet Line

Central Secretariat – Sarita Vihar : with effect from 3rd October 2010 (Phase – II).

Central Secretariat – Sarita Vihar : with effect from 3rd October 2010 (Phase – II).

Central Secretariat – Kashmere Gate (Line-6 Extension) 
Central Secretariat – Janpath- Mandi House : with effect from 28th June 2014 (Phase – III).

Sarita Vihar to Badarpur : With effect from 14th January 2011 (phase-II).

ITO station : With effect from 8th June 2015 (phase-III).

Sarai-Escorts Mujesar(Faridabad section : with effect from 6th september 2015) Phase III

Delhi Gate –Kashmere Gate with effect from 28th May 2017 Phase III

  • Line 6 (Escorts Mujesar to Raja Nahar Singh (Ballabhgarh) Section) – Violet Line 

With Effect from 19th November 2018 (Phase – III) .

  • Airport Metro Express Line

New Delhi – IGI Airport(T-3)- Dwarka Sector-21 With Effect from 23rd February (Phase – II) 2011.

  • Line 8 (Botanical Garden- Kalkaji Mandir Section) – Magenta Line

With Effect from 25th December 2017 (Phase – III) .

  • Line 8 (Kalkaji Mandir – Janakpuri West Section) – Magenta Line

With Effect from 28th May 2018 (Phase – III) .

  • Line 7 (Majlis Park to Durgabhai Deshmukh South Campus Section) – Pink Line

With Effect from 14th March 2018 (Phase – III) .

  • Line 7 (Durgabhai Deshmukh South Campus to Lajpat Nagar Section) – Pink Line

With Effect from 06th August 2018 (Phase – III) .

  • Line 7 (Trilokpuri-Sanjay Lake to Shiv Vihar Section) – Pink Line

With Effect from 31th October 2018 (Phase – III) .

More Information

Phase I Network

Phase I of Delhi Metro Rail project consists of the following three lines:

Line Length (Kms) No. of Stations
Line No.1- Shahdara-Tri Nagar-Rithala 22.06 18
Line No.2- Vishwa Vidyalaya-Central Secretariat 10.84 10
Line No.3- Indraprastha-Barakhamba Road-Dwarka Sub City 32.10 30
Total 65.00 58

Phase II Network

Phase II of Delhi Metro Rail project consists of the following lines:

Line Length (Kms) No. of Stations
Shahdara – Dilshad Garden 3.09 3
Indraprastha – Noida Sector 32 City Centre 15.07 11
Yamuna Bank – Anand Vihar ISBT 6.17 5
Vishwavidyalaya – Jahangir Puri 6.36 5
Inderlok – Kirti Nagar -Mundka 18.46 16
Central Secretariat – HUDA City Centre 27.58 19
Dwarka Sector 9 to Dwarka Sector 21 2.76 2
Airport Express Line 22.70 6
Anand Vihar – KB Vaishali 2.57 2
Central Secretariat – Badarpur 20.16 16
Total 124.93 85

PHASE III PROJECTS (Last Updated:12.11.2018)